Fortis Roofing Farnborough 01252 596302 Get a quote

Roof replacement answer

The 25% Re-Roofing Rule Explained

People often quote the 25 per cent figure on its own. The real test has two limbs, and some councils frame the question differently again.

The short answer

The 25% rule is half of a two-part test. The Planning Portal says no building control application is normally needed if less than 25 per cent of the building envelope and less than 50 per cent of the roof is affected. Both limits apply together. Quoting only the 25 per cent figure, as many pages do, gives a wrong picture of the national test.

Two limits, not one

The Planning Portal sets the test out in its terraced-house roof guide. Its wording is that less than 25 per cent of the total building envelope must be affected, and less than 50 per cent of the roof. The word "and" joins the two, so a job has to pass both before building control is normally off the table.

The building envelope means everything that wraps the house: each wall, the floor, the roof, the windows, the doors and any roof windows. A roof is only one part of it. A big roof slope on a small house can use up the envelope limit even while the roof limit still looks safe, which is why neither number works alone.

Reading the test needs a measured area, not a guess. At the survey we measure and photograph every slope, so the share being re-covered is a figure taken from your own house. The test also covers only the ordinary case. The Planning Portal sets separate triggers that have nothing to do with area, and the next section covers them, along with how the portal words each one.

Where the common misquote goes wrong

The usual misquote squeezes the rule into one line about the roof alone. That mixes up the two limbs. The 25 per cent figure belongs to the whole building envelope, while the roof has its own separate limit of 50 per cent. Neither figure is a universal line that settles every job.

The same Planning Portal guidance adds triggers that ignore area altogether. Approval follows if the replacement material weighs 15 per cent or more than what came off, or if the way it behaves in a fire differs markedly from the covering it replaces. On weight, the portal tells owners to consult an engineer or a surveyor ahead of the work, and we would add that the answer should be in writing. Approved Document A words its own threshold as a loading increase of more than 15%, so the two documents differ by a word and each deserves to be quoted by name.

That makes the rule a prompt to check, not a promise that a small job escapes. Swapping concrete tiles for natural slate, or the reverse, is the case where weight deserves a look first.

Councils that list re-covering by name

None of the councils around Farnborough sets a percentage of its own. Rushmoor, whose building control team is shared with Hart, gives no re-roofing rule on its page and points readers to the Planning Portal interactive guides. For Farnborough and Aldershot addresses, the national test is the one to use.

A few other councils frame the work differently. Bracknell Forest tells owners they may also need building regulations approval when replacing roof coverings, and it names pitched and flat roofs. Basingstoke and Deane counts new roof coverings among the alteration projects where approval could be needed. The Royal Borough of Windsor and Maidenhead (RBWM) names the re-tiling or re-felting of a roof under thermal elements, and adds a second entry for tiles that are heavier or lighter than the old ones.

Each of those statements belongs to that council and its own addresses. None of them says approval is always needed, and none gives a percentage. Where a house sits in one of those three areas, we read the council's wording before the job starts rather than relying on the national shorthand, and we say in the written scope which route applies.

What it means for your quote

For most whole-roof replacements the question answers itself, because a complete strip and re-cover affects more than half of it. Then a building control application is the route to expect, and it is worth asking early who will handle it and what the council charges for the inspections, since that cost is best known before you commit. A renovated roof may also need to meet the energy standards for thermal elements, which our page on insulation when re-roofing covers.

A smaller job, such as a single slope, is where the two limbs start to matter. Our page on replacing half a roof shows how that plays out, and heavier roof coverings explains the weight trigger in more detail.

We put the scope in writing after the survey and give one total price, and the scope says which approval route the job falls under. Our roof replacement page shows how a job runs from survey to the final tidy-up. If your council is not one of those named above, ask its building control team before you sign anything, and keep the reply with your paperwork.

Checking the rule before work starts

Does the 25 per cent figure apply to the roof or the whole house?

It applies to the whole building envelope: walls, floor, roof, windows, doors and roof windows together. The roof has a separate limit of 50 per cent, and the Planning Portal says both must be met. Reading 25 per cent as a share of the roof alone is the common mistake, and it can send an owner the wrong way.

Does a re-roof under the limits still need planning permission?

That is a separate question from building control. Class C of the permitted development rights deals with roof alterations to dwellinghouses, so re-covering a house roof is normally allowed. Flats have no permitted development rights, and conservation areas and Article 4 directions can change the answer, so ask your planning team.